The latest statistics on planning application decision-making and timescales for quarter 1 of 2017 and data going back to quarter one of 2013-2014.

31 page PDF

1.5MB

31 page PDF

1.5MB

Contents
Planning performance statistics: first quarter, 2017-2018
4. Processing Agreements

31 page PDF

1.5MB

4. Processing Agreements

Some local authorities use processing agreements where the developer and the local authority agree on timescales for decisions. When an application is subject to a processing agreement it is removed from average decision time calculations and reported separately. In quarter one of 2017/18 there were 471 applications that were subject to a processing agreement, and 80.3 per cent of these were decided within agreed timescales ( Quarter 1, 2017/18 – Table 1).

Table 1: Processing Agreements, 2017/18, Quarter 1

Category of development Number of Decisions % Within Agreed Timescales
Major Applications 26 69.2%
Local Applications 379 81.5%
EIA Developments 2 100.0%
Other Consents 64 76.6%
Total 471 80.3%