Planning performance statistics: second quarter, 2017-2018

Published: 30 Jan 2018

The latest statistics on planning application decision-making and timescales from July to September 2017-2018.

31 page PDF

4.1 MB

31 page PDF

4.1 MB

Contents
Planning performance statistics: second quarter, 2017-2018
4. Processing Agreements

31 page PDF

4.1 MB

4. Processing Agreements

Some local authorities use processing agreements where the developer and the local authority agree on timescales for decisions. When an application is subject to a processing agreement it is removed from average decision time calculations and reported separately. In quarter two of 2017/18 there were 532 applications that were subject to a processing agreement, 61 (13 per cent) more than in the previous quarter, and 80.5 per cent of these were decided within agreed timescales ( Quarter 2, 2017/18 – Table 1).

Table 1: Processing Agreements, 2017/18, Quarter 2

Category of development Number of Decisions % Within Agreed Timescales
Major Applications 23 78.3%
Local Applications 423 81.3%
EIA Developments 1 100%
Other Consents 85 76.5%
Total 532 80.5%

 